In high-rise buildings, the axial deformations of columns cannot be ignored, and special consideration is required for construction and design. In this session, we will cover the construction stage analysis for column shortening. We can also see how midas Gen considers construction stage analysis with creep & shrinkage effect.
Dead Load is Sequential Loading
Time-Dependent Material Properties (Elastic Modulus, Creep, and Shrinkage)
Compensation for Differential Column Shortening
Comparison between with and without considering sequential loading
Reasons and Effects of Column Shortening
Pre-Analysis
- Preliminary Analysis
Main Analysis, Construction & Re-Analysis
-Material Experiment
-Main analysis
-Measurement
-1st, 2nd, 3rd Re-Analysis
-Final Report
Compensation at Site
Burj Khalifa (Dubai, UAE)
SK S-Trenue (Seoul, Korea)
Keangnam Hanoi Landmark Tower (Hanoi, Vietnam)
Define materials, sections
Assign elements, boundaries & loads to the groups
Define time-dependent materials
Enter the construction stage analysis data
Perform an analysis
Check results for each construction stage
Check column shortening
Live, wind and seismic loads are applied at once to the entire complete structure. However, Dead load is a type of sequential loading as shown in this slide. Since most buildings are constructed by one story or several floor units at a time, we need to consider the construction sequence in analysis. Therefore the actual structural behavior can be significantly different from the conventional analytical behavior.
There are 4 reasons which occur column shortening.
–Elastic stresses due to gravity loads
–Creep caused by gravity load
–Drying shrinkage
–Temperature variations of exposed columns
Among those, shortening due to Creep & Shrinkage will be happened only in the concrete buildings. Due to high stresses, the elastic shortening of the steel column is higher than the shortening of the concrete column. In the concrete columns, the shortening due to shrinkage and creep comprise respectively 36% and 28% of total shortening.
Thanks for registration.
The registration confirmation email has been sent to your email
Thanks for registration.
Please check the confirmation email from GoToWebinar for joining the session.
a. Information Processed
The minimum amount of personal information required for the provision of the service is being collected. In the process of the sign-up for membership or the use of the service, the Company is collecting the minimum amount of personal information required to provide the service through a separate application or program as follows:
Processing Personal Informationb. Method of Collection
When collecting the personal information, the Company makes sure to inform the user in advance and request for the user’s approval. The personal information is being collected in the following ways:
The personal information to be collected from the user in using the service is as follows:
The Company uses the personal information for the following purposes including managing membership, providing and improving customized services, calculating fees incurred for the services, developing new services, and providing information for service-related events and promotion; provided, however, that the Company shall not use the member’s personal information if the member has expressed his/her intention that he/she does not want to provide the information for service-related events and promotion. The Company shall not be held liable for any disadvantage that may arise to the member as a result thereof.
The personal information shall be destroyed upon achievement of the purposes of collecting and using it, and the procedures and methods for destruction is as follows.
The personal information stored in the form of an electronic file will be deleted so that such information shall not be restored and reproduced. Other records, print-outs, written documents will be shredded and incinerated; provided, however, that the data that will be stored for a certain period of time in accordance with internal policy are as follows:
Records to be Retained | Grounds of Retention | Period of Retention |
---|---|---|
Records on agreement and withdrawal | Act on the Consumer Protection in | 5 years |
Records on payment and product supplies, etc. | Electronic Commerce, etc. | 5 years |
Records on consumer complaints or dispute handling | 3 years | |
Records on marks/advertisement | 6 months | |
Books and evidential documents on all transactions as specified in tax law | Framework Act on National Taxes | 5 years |
Books and evidential documents on all transactions as specified in tax law | Framework Act on National Taxes | 5 years |
Records on electronic financial transactions | Electronic Financial Transactions Act | 5 years |
Records on log-in history in connection with the use of the service | Protection of Communications Secrets Act | 3 months |